Oracle Planning Central Cloud Service 2018 Implementation Essentials - 1Z1-1028 Exam Practice Test
Question 1
In order for Supply and Demand Plans to run successfully, which three Configure Planning Analytic tasks must be completed? (Choose three.)
Correct Answer: A,E,F
Question 2
You want to understand what your inventory turns are for your organization. Where can you see this information in Planning Central?
Correct Answer: D
Question 3
As a new planner, you want to test simulation set functionality. You have created a simulation set named 'Test Simulation Set.' In this simulation set, you have already added Item 98573. You would like to change the item specification 'Fixed Order Quantity' to 10 within this simulation set.
Which sequence will allow you to accomplish this task?
Which sequence will allow you to accomplish this task?
Correct Answer: B
Question 4
Your customer wants to display a numeric measure in both pound and kilogram Units of Measure (UOM) on a table. Describe the configuration steps to display a measure in two UOMs.
Correct Answer: B
Question 5
Your customer wants to be able to manually change the input values in purchase orders and transfer orders for the suggested plan recommendations. Which two recommendations are released by supply chain planning to Oracle Supply Chain Orchestration Cloud? (Choose two.)
Correct Answer: B,D
Question 6
You are setting up the plan page layout for your customer.
In which of these requirements would you use an Infotile?
In which of these requirements would you use an Infotile?
Correct Answer: E
Question 7
Your client wants their supply plans to have a customized group of exceptions. What two steps must you complete in order to make sure only these exceptions are included when running all of your client's supply plans? (Choose two.)
Correct Answer: C,D
Question 8
During the FIFO pegging process, what is the correct order in which the supplies are sorted?
Correct Answer: D