Question 1
Among the various functions provided by progress tracking that simplify data entry and analysis which function allows you to go the master data display for objects that are underlined?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 2
What are the three tables that are defined for order type in network costing?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
Question 3
In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,D
Question 4
Which combination allows you to assign the material components in one WBS element to different grouping WBS element?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C,D
Question 5
Which of the following can be derived automatically when you carry out scheduling in projects with networks?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
Question 6
If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,B
Question 7
Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 8
Assume you have created a sales order for a material to which a strategy group for assembly processing has been assigned and the system automatically created a so-called assembly order in the background and started assembly processing.
In this case, the assembly processing omits which stage and generates an operative order directly from the sales order?
Please choose the correct answer.
Response:
In this case, the assembly processing omits which stage and generates an operative order directly from the sales order?
Please choose the correct answer.
Response:
Correct Answer: B
Question 9
The determination of the settlement profile and result analysis key is based on WBS-operative indicators for which of the following?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
Question 10
Which of the following scenario doesn't allow the plan value of the order to be added to the committed value of the WBS element until the order has the status released?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 11
Which of the following are used when you use the SAP Document Management System in Project System to assign document info records?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
Question 12
In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 13
When the system derives settlement rules, it generates profitability segments that contain the characteristic values of which of the following assigned to them?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C