SAP Certified Application Associate - SAP S/4HANA Project Systems - C-TS412-1909 Exam Practice Test
Question 1
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
Correct Answer: B
Question 2
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
Correct Answer: D
Question 3
Cost & Budget
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.
Correct Answer: D
Question 4
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question
Correct Answer: A,B
Question 5
How can you update the degree of processing for an activity?
Correct Answer: D
Question 6
How can you grant individual authorization for WBS elements and networks?
Correct Answer: A
Question 7
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
Correct Answer: B
Question 8
You have saved a network and activates with assigned material components. As soon as you release the network,
you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
Correct Answer: A
Question 9
The various work packages in the project are described as individual______________. Choose the correct answer.
Correct Answer: A
Question 10
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.
Correct Answer: C,D