SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (1709) - C-TS420-1709 Exam Practice Test
Question 1
In which customizing activity do you set up automatic routing selection for production orders?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Question 2
What are some of the SAP Fiori user types?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Question 3
What must be used in the system to plan the requirements for different subcontractors separately?
Response:
Response:
Correct Answer: C
Question 4
In which of the following master data objects can you define the production order default storage
location for a material component?
There are 2 correct answers to this question.
Response:
location for a material component?
There are 2 correct answers to this question.
Response:
Correct Answer: A,B
Question 5
Which of the following is used by the MRP Live planning run in SAP S/4HANA?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Question 6
Which data object can be updated with the scheduling results of a routing?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Question 7
When the goods receipt for a finished product is posted during confirmation on a manufacturing
environment, which of the following actions are also performed by default?
There are 2 correct answers to this question.
Response:
environment, which of the following actions are also performed by default?
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
Question 8
For which data objects do you have to set up CIF integration models in S/4HANA to use them in
advanced planning?
There are 2 correct answers to this question.
Response:
advanced planning?
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
Question 9
At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused
the message to be generated?
Please choose the correct answer.
Response:
the message to be generated?
Please choose the correct answer.
Response:
Correct Answer: C
Question 10
Which reports can you access via the order and resource reporting transaction in advanced planning?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,C