APICS Certified in Production and Inventory Management - CPIM Exam Practice Test

Question 1
At the MRP planning level, the process of priority plans must be checked against available capacity is called

Correct Answer: C
Question 2
Where-used reports give information about

Correct Answer: D
Question 3
Production planning problem typically has the following characteristics EXCEPT:

Correct Answer: C
Question 4
What involves long-range capacity resource requirements and is directly linked to production planning?

Correct Answer: B
Question 5
What is responsible for executing the master production schedule and the material requirements plan?

Correct Answer: B
Question 6
The emphasis in just-in-time is on achieving the plan, no more, no less, this is called:

Correct Answer: A
Question 7
A pegging report:

Correct Answer: D
Question 8
The formula to calculate the Inventory turns is:

Correct Answer: D
Question 9
Which costs can be avoided by leveling production, that is, by producing items in slack periods for sale in peak periods?

Correct Answer: D
Question 10
Sales 100 100 100 100 100 100
Production 200 200 200 100 100 100
Starting Inventory = 100
The production plan shown above is an example of which production strategy?

Correct Answer: B
Question 11
The absence of defects both in product and non-product categories and use of a good documentation system, this is known as:

Correct Answer: A
Question 12
Work done at each workstation should take about the same time, this is called:

Correct Answer: D