SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 - C_TPLM22_67 Exam Practice Test
Question 1
The determination of the settlement profile and result analysis key is based on WBS-operative indicators for which of the following?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
Question 2
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 3
Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 4
Which indicator determines whether summarization is executed on the basis of classification or master data characteristics; in a network profile?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 5
Which of the following levels can you assign persons to work centers?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
Question 6
In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 7
You use a WBS Project Structure with networks and maintenance orders. You want to Schedule both the networks and the maintenance orders. What do you consider? *
Correct Answer: B
Question 8
What should you call up to view all the information on an active or completed job that was scheduled in the scheduler in schedule manager?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Question 9
Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 10
In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.
How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?
Please choose the correct answer.
Response:
How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?
Please choose the correct answer.
Response:
Correct Answer: B
Question 11
How can you update the degree of processing for an activity?
Correct Answer: C