Question 1
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?
Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 2
How can you characterize dependent requirements in material requirements planning?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
Correct Answer: B,C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 3
How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.
Note: There are 2 correct answers to this question.
Correct Answer: B,C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 4
What can you use heuristics in Advanced Planning (PP/DS) for?
Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 5
Where do you maintain the work center that represents the production line for repetitive manufacturing?
Note: There are 2 correct answers to this question
Note: There are 2 correct answers to this question
Correct Answer: B,D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 6
You want to schedule an operation finitely, without removing other operations. Which scheduling strategy do you select?
Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 7
Generic Parent Generic 1 pt
What is the purpose of collective orders?
What is the purpose of collective orders?
Correct Answer: B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 8
Which standard item categories can you select inside a bill of material (BOM)?
Note: There are 2 correct answers to this question
Note: There are 2 correct answers to this question
Correct Answer: A,D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 9
You Have a scheduling agreement with a vendor, you want classic MRP to automatically create schedule lines in case of material shortage, what must you do?
Note: there are 2 correct answers to this question.
Note: there are 2 correct answers to this question.
Correct Answer: A,B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).