Nokia CPM - PDM_2002001060 Exam Practice Test
Question 1
Which of the following is NOT an example of cost of poor quality?
Correct Answer: D
Question 2
The project team has received the LoA approved risk log, which is the basis for the cost baseline risk contingency. During project execution a new relevant risk is identified. What is the best way to manage it?
Correct Answer: A
Question 3
To meet the requirements of the project through effective contract management, it is best to:
Correct Answer: D
Question 4
What is the back-to-back principle that Nokia implements for project vendor contracts?
Correct Answer: A
Question 5
Which of the following inputs are used for Resource Planning?
Correct Answer: C
Question 6
What is the best timing to review the estimate at completion (EAC)?
Correct Answer: D
Question 7
The project is not completed until:
Correct Answer: C
Question 8
What is the required action when a project is being delayed for 6 weeks due to problems in the infrastructure to be provided by the customer?
Correct Answer: A
Question 9
If a customer requests a consistency check to the network design, which was not included in Nokia scope of work, what is the appropriate action?
Correct Answer: A
Question 10
What is the purpose of change management?
Correct Answer: D
Question 11
The estimated value of the work actually accomplished is:
Correct Answer: C
Question 12
Which of the following are key components of a Site Process?
Correct Answer: C
Question 13
What is the correct GIC to plan costs related to payment of a subcontractor responsible for BTS commissioning?
Correct Answer: B

