Question 1
The program director of a four-year program, estimated to require 600.000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the last phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation Which of the following metrics should the PMO capture on a monthly basis?
Correct Answer: D
Question 2
A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company's headquarters Five regional sales departments are located at different locations around the world.
At this stage of the program, what is the first step?
At this stage of the program, what is the first step?
Correct Answer: B
Question 3
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?
What should be done with the identified potential risk?
Correct Answer: B
Question 4
A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million.
Since the shutdown was not anticipated, what should the program manager do first?
Since the shutdown was not anticipated, what should the program manager do first?
Correct Answer: D
Question 5
During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and
Correct Answer: B
Question 6
You are designing a multi-story dwelling and need to place the CTR's. Every floor is not available. What is the alternate spacing for the CTRs?
Correct Answer: E
Question 7
During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers. The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?
Correct Answer: D
Question 8
Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?
Correct Answer: D
Question 9
The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.
Which of the following should the program manager do first?
Which of the following should the program manager do first?
Correct Answer: A
Question 10
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment Where should the program manager document this?
Correct Answer: A
Question 11
A manufacturing company is redesigning various component projects that comprise a large customer-facing program. One of the component projects is payment of back-end rebates. There is disagreement between the marketing and sales teams on how much should be rebated.
What are suggested standard measurement criteria for the success of all constituent projects to meet stakeholder expectations''
What are suggested standard measurement criteria for the success of all constituent projects to meet stakeholder expectations''
Correct Answer: B
Question 12
A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.
What should the program manager do next to address this risk?
What should the program manager do next to address this risk?
Correct Answer: C
Question 13
A non-profit organization launched a program to reduce its dependence on regularly decreasing government funding sources. This program's goal was (o raise 50 percent of its operating expenses by selling its services to the for-profit sector. After three years, the goal was reached, deemed complete, and transitioned to operations.
Eighteen months later, the organization discovers that its dependence on government funds has now increased to 80 percent, even though its operating budget has largely stayed the same What should the program manager have done to avoid the issue of program benefits being unrealized after more than a year of implementation?
Eighteen months later, the organization discovers that its dependence on government funds has now increased to 80 percent, even though its operating budget has largely stayed the same What should the program manager have done to avoid the issue of program benefits being unrealized after more than a year of implementation?
Correct Answer: A
Question 14
A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.
What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?
What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?
Correct Answer: B
Question 15
An IT-related program has a critical team in a region experiencing a crisis. Due to uncertainty about the region's changing environment a company's senior leadership asks the program manager to decrease dependencies on the critical team that should the program manager do to mitigate the Impacts of this request?
Correct Answer: C