BICSI Registered Communications Distribution Designer - RCDD v15 - RCDDv15 Exam Practice Test

Question 1
An ICT distribution designer is representing a client during a project execution.
What is the designer's role in the Vendor and Contractor Coordination?

Correct Answer: B
Question 2
CORRECT TEXT
A program manager joins a team during its preparation phase.
What should the program manager do lo obtain formal sponsor approval to begin the benefits delivery phase1?

Correct Answer: C
Question 3
Near the completion of a transformation program, the operations manager is concerned that their department failed lo be notified in advance of the new service being transitioned into operations. They claim that their department did not approve this service and is now unprepared and untrained to support the transformation.
What should the program manager have done first to prevent this?

Correct Answer: A
Question 4
A program manager assigns project managers lo five component projects and continues to develop the program team.
Which of the following represents the program manager's strategy?

Correct Answer: A
Question 5
What is a passive optical network (PON)?

Correct Answer: C
Question 6
A utility company manages its capital improvement projects (CIP) using engineers, project managers, and program managers. A new sponsor from the utility company assesses the CIP and decides to reorganize it into a program. They invite seven companies to discuss their approach to monitor and control the program and its constituent protects.
Where should the program manager incorporate this input?

Correct Answer: A
Question 7
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?

Correct Answer: B
Question 8
The program selection committee presents several programs for approval:

Which program was selected based solely on a three-year return on investment?

Correct Answer: C
Question 9
The program manager takes over a poorly performing program After a review of the documentation and interviews with the program sponsor, stakeholders and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent protects and components to meet the program's needs
What action should the program manager take to realign the program?

Correct Answer: B
Question 10
In a transformational program, all projects are on track and delivering their objective. However stakeholders are hesitant to take on the new processes because performance in the current environment may not be representative of actual performance Stakeholders fear that the program will fail to provide the service required.
To assure positive performance in the current environment, the program manager should do which of the following?

Correct Answer: C
Question 11
Which of the following two items are examples of items associated with a submittal? (Select two options.)

Correct Answer: D,E
Question 12
To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company's CEO endorses a new program to promote and support this strategy However before the program is formally initialed, this strategy must be aligned with the organization's strategic goals and objectives.
What should the program manager develop first?

Correct Answer: B
Question 13
When considering pathway types, the ICT distribution designer should consider the applicable MICE factors as defined in TIA 568 for structured cabling systems and
components MICE 3 relates to

Correct Answer: B
Question 14
A system integration approach of a BAS on to a LAN can usually reduce the cost of cabling-related changes by

Correct Answer: C