Question 1
You are a project manager who uses Project Professional 2013.
You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks.
You need to monitor this phase closely to ensure that it does not overrun.
What should you do?
You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks.
You need to monitor this phase closely to ensure that it does not overrun.
What should you do?
Correct Answer: E
Question 2
You are a project manager who uses Project Professional 2013.
You work in a software development project, which is in progress and has reached 60% of actual progress. Your company decides to use the new Project Reports views to communicate all the project progress across the key users. They also decide to report information about a specific period only, normally one month behind the current day.
You need to access the report view that your company previously created; however, you must only modify the period displayed in the report and ensure that another period will not be presented.
What should you do?
You work in a software development project, which is in progress and has reached 60% of actual progress. Your company decides to use the new Project Reports views to communicate all the project progress across the key users. They also decide to report information about a specific period only, normally one month behind the current day.
You need to access the report view that your company previously created; however, you must only modify the period displayed in the report and ensure that another period will not be presented.
What should you do?
Correct Answer: D
Question 3
You manage a project by using Project Standard 2013.
You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2.
What should you do?
You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2.
What should you do?
Correct Answer: A
Question 4
You are a project manager who uses Project Standard 2013.
You regularly customize the Bar Styles for a project prior to printing the project schedule.
You need to add the Bar Styles button to the Quick Access Toolbar as quickly as possible.
What are two ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
You regularly customize the Bar Styles for a project prior to printing the project schedule.
You need to add the Bar Styles button to the Quick Access Toolbar as quickly as possible.
What are two ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
Correct Answer: B,C
Question 5
You manage a project and use Project Professional 2013 to track your project schedule.
One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at
50% of their availability.
The resource asks to start the task three days later than planned because of a scheduling conflict. The schedule change is approved.
You need to make the adjustment to the resource assignment to accommodate this request without affecting the other resources assigned to the task.
What should you do?
One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at
50% of their availability.
The resource asks to start the task three days later than planned because of a scheduling conflict. The schedule change is approved.
You need to make the adjustment to the resource assignment to accommodate this request without affecting the other resources assigned to the task.
What should you do?
Correct Answer: B
Question 6
You are an independent project manager who uses Project Professional 2013.
You work on multiple projects for different customers and use only one project to manage their tasks. You invoice your customers on a monthly basis. To identify tasks that have not been invoiced, you create a custom field called Not Invoiced.
Without losing the original project tasks' sort order, and without hiding any information, you need to see all tasks which have not been invoiced.
You create a custom filter based on the Not Invoiced custom field.
What should you do next?
You work on multiple projects for different customers and use only one project to manage their tasks. You invoice your customers on a monthly basis. To identify tasks that have not been invoiced, you create a custom field called Not Invoiced.
Without losing the original project tasks' sort order, and without hiding any information, you need to see all tasks which have not been invoiced.
You create a custom filter based on the Not Invoiced custom field.
What should you do next?
Correct Answer: A
Question 7
You are a project manager who uses Project Professional 2013.
Your organization migrates all project plans from Microsoft Excel to Project Professional
2013. One of the directors of the company has several years of experience using Excel Pivot Tables to analyze and make decisions about projects.
You need to enable project managers to view relevant project information in Excel Pivot Tables.
What should you do?
Your organization migrates all project plans from Microsoft Excel to Project Professional
2013. One of the directors of the company has several years of experience using Excel Pivot Tables to analyze and make decisions about projects.
You need to enable project managers to view relevant project information in Excel Pivot Tables.
What should you do?
Correct Answer: B