Oracle Project Management Cloud 2025 Implementation Professional - Delta - 1D0-1057-25-D Exam Practice Test

Question 1
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

Correct Answer: B
Question 2
You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)

Correct Answer: A,B
Question 3
You cannot generate invoices for a project expenditure item. After running the Generate Invoices program for a billable expenditure item and active contract, the process completes successfully but without any billing, and does not provide any error logs.
The program's processing summary is as follows:
Billing Event Errors 0
Ineligible Contracts 0
Successfully Billing Events Created 0
Ineligible Contract Lines 0
Billing Transaction Exception Errors 0
Ineligible Bill Plans 0
Billing Transaction Exception Warnings 0
Ineligible Associated Projects 0
Successful Billing Transactions 0
Ineligible Expenditure Items 0
Draft Invoice Exception Errors 0
Ineligible Events 0
Draft Invoice Exception Warnings 0
Successful Draft Invoices 0
What was the invoice method classification set to that caused this behavior? (Choose the best answer.)

Correct Answer: D
Question 4
Your organization has decided to enable the common accounting and project accounting periods option while defining business unit implementation options.
Where will you maintain the accounting period statuses if this option has been enabled?

Correct Answer: C
Question 5
You are currently involved in the implementation of the Project Financial Management solution for your client organization. Your client organization has two main lines of business: Consulting and Support. Consulting Services and Support Services organizations have different project planning, management, analysis and reporting requirements for the projects that they manage, though the management reporting and transaction processing requirements are the same for both the organizations.
What will be your recommendation?

Correct Answer: B
Question 6
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattem and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)

Correct Answer: C
Question 7
Your client has decided to import time cards into Project Costing from Oracle Fusion Time and Labor. They have a requirement to make adjustments to time card entries whenever needed.
In which work area will the employees and contingent workers be able to modify their time cards?

Correct Answer: A