AACE International Planning & Scheduling Professional (PSP) - AACE-PSP Exam Practice Test

Question 1
Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?

Correct Answer: D
Question 2
The linear scheduling velocity diagram has the following two-axis:

Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 3
If all other work proceeds according to the Baseline plan, how many times will the critical path change?

Correct Answer: A
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 4
Which of the following is NOT true?

Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 5
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

Correct Answer: B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 6
Baseline schedule can be submitted only__________.

Correct Answer: D
Question 7
Who can define KPls?

Correct Answer: C
Question 8
When should the Project Plan have incorporated the relevant interfaces and requirements of the project contract documents?

Correct Answer: D
Question 9
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 10
The addition of which of the following relationships would cause a logic loop?

Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 11
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

Correct Answer: A
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 12
What is the result of a forward pass calculation?

Correct Answer: A
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 13
During the Bid Phase, do the planning and scheduling project documents impact the Bid pricing?

Correct Answer: C
Question 14
Determine the correct formula and date for the late start for Activity 9001.

Correct Answer: B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 15
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).