Question 1
What are the pre-requisites for distributing work to HR Resources?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
Question 2
How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
Question 3
What are the various transactions in SAP PS with which a work breakdown structure can be created?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,C
Question 4
Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 5
What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 6
An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Question 7
In which type of project stock G/L account determination for project stock is controlled differently from collective stock using specific valuation classes for sales order stock and project stock in the material master?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,D
Question 8
In resource-related billing if you do not want to bill a customer for a dynamic item, where do you enter this information?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Question 9
Which of the following scenario doesn't allow the plan value of the order to be added to the committed value of the WBS element until the order has the status released?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Question 10
What are the three tables that are defined for order type in network costing?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
Question 11
What are the different views available for capacity planning and work center planning?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
Question 12
Which of the following levels can you assign persons to work centers?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C