ServiceNow Certified Implementation Specialist - Project Portfolio Management (PPM) - CIS-PPM Exam Practice Test
Question 1
A pps_admin role can configure the parameters that are displayed on a project card. The parameters displayed on a project card are derived from the records in what table?
Correct Answer: D
Question 2
The Project Portfolio Management application supports domain separation at this level:
Correct Answer: C
Question 3
In the base system, what is the default number of cards that can be displayed in the project workspace?
Correct Answer: D
Question 4
What is the default schedule for a project?
Correct Answer: A
Question 5
Which plugin provides a layer of artificial intelligence that empowers features and capabilities across applications to provide better work experiences?
Correct Answer: A
Question 6
What happens to the expense line after it is processed?
Correct Answer: B
Question 7
How does a project manager request a change to a resource plan in the requested state?
Correct Answer: C

