APICS Execution and Control of Operations - CPIM-ECO Exam Practice Test
Question 1
Which of the following project characteristics would suggest using the PERT technique, rather than the critical path method?
Correct Answer: B
Question 2
If an operation on a routing is performed out of sequence and the change in sequence is not reported to the formal system, which of the following situations will occur?
Correct Answer: C
Question 3
Which of the following performance metrics best measures customer satisfaction?
Correct Answer: C
Question 4
The utilization of a downstream nonbottleneck resource is determined by:
Correct Answer: B
Question 5
Managing the constraint in an operation will improve which of the following metrics?
Correct Answer: B
Question 6
A company has implemented a corrective action to one of four production lines. Before implementing the change to the other lines, which of the following actions should be taken?
Correct Answer: D
Question 7
In a work center that requires a large number of tooling changes, the best way to increase productivity is to:
Correct Answer: A
Question 8
Which of the following statements about the MRP due date for a shop order is true?
Correct Answer: C
Question 9
Which of the following methods is used to sequence jobs planned for production within the same time period?
Correct Answer: B