PMI Risk Management Professional - PMI-RMP Exam Practice Test
Question 1
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.
What is the current project risk exposure?
What is the current project risk exposure?
Correct Answer: B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 2
What should the risk owner use as an effective information-gathering technique during the planning session?
Correct Answer: A
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 3
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?
What process is this part of?
Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 4
In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers this a low-impact issue because many construction materials providers can fulfill the project demands.
However, after informing the stakeholders of this issue, the major investor is about to drop their intention to continue executing the project. The risk manager does not understand their decision.
What should the risk manager do next to understand the major stakeholder ' s decision regarding the project?
However, after informing the stakeholders of this issue, the major investor is about to drop their intention to continue executing the project. The risk manager does not understand their decision.
What should the risk manager do next to understand the major stakeholder ' s decision regarding the project?
Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 5
A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.
What type of risk is this?
What type of risk is this?
Correct Answer: A
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 6
A risk manager is conducting a qualitative risk analysis for a renewable energy project that faces tight deadlines. The team identifies risks such as weather unpredictability, material cost fluctuations, and potential regulatory delays. While some members advocate prioritizing high-likelihood risks, others emphasize addressing unlikely but high-impact risks.
What should the risk manager do?
What should the risk manager do?
Correct Answer: B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 7
A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule.
One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.
What should the risk manager do to address this situation?
One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.
What should the risk manager do to address this situation?
Correct Answer: B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 8
A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.
How should the risk manager explain the need for a risk strategy specific to this project?
How should the risk manager explain the need for a risk strategy specific to this project?
Correct Answer: B
Question 9
A risk manager is confident that they have identified and quantified the risks and opportunities for a project.
When presenting their work to management, on what areas should the risk manager focus? (Choose two.)
When presenting their work to management, on what areas should the risk manager focus? (Choose two.)
Correct Answer: A,E
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 10
A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.
What type of risk is being referred to here?
What type of risk is being referred to here?
Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 11
After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.
What should the risk manager do to facilitate the sponsor ' s ask?
What should the risk manager do to facilitate the sponsor ' s ask?
Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 12
After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?
Correct Answer: A
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 13
A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.
Which kind of numerical analysis should be performed to understand the worst-case scenarios?
Which kind of numerical analysis should be performed to understand the worst-case scenarios?
Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 14
While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?
Correct Answer: A
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).

