Scrum Professional Scrum Master I - PSM-I Exam Practice Test

Question 1
User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do?
(choose the best answer)

Correct Answer: B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 2
During Sprint Planning the Product Owner and the Developers are unable to reach an understanding about the highest order Product Backlog items. Because of this, the Developers are unable to determine how many Product Backlog items they can forecast for the upcoming Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.
Which of the following actions should the Scrum Master support?
(choose the best two answers)

Correct Answer: A,C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 3
What does it mean for a Scrum Team to be cross-functional?
(choose the best answer)

Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 4
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 5
What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)

Correct Answer: A,B
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 6
What is the recommended size for a Development Team?

Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 7
What are two ways that regulatory compliance issues are dealt with in Scrum?
(choose the best two answers)

Correct Answer: B,C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 8
Which of the following are true about the length of the Sprint? (Choose two.)

Correct Answer: A,E
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 9
Sprint burndown charts are an efficient tracking tool, because they show:

Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 10
What is the function or purpose of management in Scrum?
(choose the best answer)

Correct Answer: A
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 11
Who must attend the Daily Scrum?

Correct Answer: C
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).
Question 12
What is the key concern when multiple Development Teams are working from the same Product Backlog?

Correct Answer: D
Explanation: Only visible for Actualtests4sure members. You can sign-up / login (it's free).