Question 1
A project manager builds consensus and overcomes obstacles by employing which communication technique?

Correct Answer: B
Question 2
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

Correct Answer: C
Question 3
An input to the Perform Integrated Change Control process is:

Correct Answer: B
Question 4
Which Process Group and Knowledge Area include the Sequence Activities process?

Correct Answer: A
Question 5
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Correct Answer: A
Question 6
Activity cost estimates are quantitative assessments of the probable costs required to:

Correct Answer: C
Question 7
Which of the following types of a dependency determination is used to define the sequence of activities?

Correct Answer: C
Question 8
The precedence diagramming method (PDM) is also known as:

Correct Answer: B
Question 9
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Correct Answer: A
Question 10
In a typical project, project managers spend most of their time:

Correct Answer: A
Question 11
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?