Microsoft Dynamics AX 2012 R2 Project - MB6-700 Exam Practice Test

Question 1
Which three statements about on-account invoices are true? (Each correct answer presents part of the solution. Choose three.)

Correct Answer: B,C,D
Question 2
You enter and post a vendor invoice. You do not know to which project to allocate the expenses.
You need to ensure that the vendor invoice will be posted with basic information and transferred to an invoice pool for approval.
Which method of managing incoming invoices should you use?

Correct Answer: B
Question 3
You create an invoice proposal and use the Manage invoice form to manage the presentment of the invoice.
Which two steps are required to group transactions with a subtotal on the invoice? (Each correct answer presents part of the solution. Choose two.)

Correct Answer: A,E
Question 4
Which statement about the customer advance feature is true?

Correct Answer: C
Question 5
You have a project with multiple funding sources.
You need to set up the allocation of funds in the project contract.
How many funding sources can you select for rounding off the differences?

Correct Answer: A
Question 6
Which item is used to transfer costs from work in process (WIP) accounts to profit and loss accounts?

Correct Answer: D
Question 7
You need to track the project costs in balance accounts until the customer is invoiced.
Which type of project should you use?

Correct Answer: B
Question 8
Which two items are determined by the cost templates for advanced fixed-price projects? (Each correct answer presents part of the solution. Choose two.)

Correct Answer: B,D