SAP C-TS412-2021 exam is designed to test the skills and knowledge of professionals who work with the SAP S/4HANA Project Systems module. SAP Certified Application Associate - SAP S/4HANA Project Systems certification is ideal for individuals who are responsible for managing and implementing project systems in their organization. C-TS412-2021 exam is designed to validate the candidate's knowledge of project planning, project execution, project cost control, and project reporting.
NEW QUESTION # 66
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
- A. Subnetworks must be scheduled separately from the superior network
- B. Maintenance orders can be defined as sub-network
- C. The scheduling type of a subnetwork is always copied from the superior network
- D. A subnetwork cannot be defined for a superior subnetwork.
Answer: C
Explanation:
One statement that describes subnetworks is that the scheduling type of a subnetwork is always copied from the superior network. A subnetwork is a network that covers only part of a project and is linked in relationships with other subnetworks in the same project. A subnetwork can be used to refine and detail your networks as planning progresses. The scheduling type is a parameter that determines how the dates of activities and networks are calculated based on their dependencies and constraints. The scheduling type of a subnetwork is always copied from the superior network when creating or changing a subnetwork. The scheduling type of a subnetwork cannot be changed independently from the superior network. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/f373bb53707db44ce10000000a174cb4.html
NEW QUESTION # 67
Cost and Budget
What function are available for period end-closing in the project System?
- A. Result analysis
- B. Settl ement
- C. Milestone trend analysis
- D. Confirmation
- E. Progress analysis
Answer: A,B,E
Explanation:
Period-end closing is a process that involves various activities to finalize the project costs and revenues at the end of a period. Some of the functions that are available for period-end closing in the Project System are:
Result analysis: This function allows you to calculate the work in process (WIP), reserves, and results for a project based on various methods and valuation rules. Result analysis also updates the financial accounting (FI) and controlling (CO) documents with the calculated values.
Progress analysis: This function allows you to measure and monitor the progress of a project based on various criteria, such as costs, revenues, dates, or quantities. Progress analysis also enables you to compare the planned and actual progress of a project and identify any deviations or delays.
Settlement: This function allows you to transfer the costs and revenues of a project to one or more receivers, such as cost centers, fixed assets, profitability segments, or sales orders. Settlement also clears the balances of the project objects and updates the corresponding accounting documents. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
NEW QUESTION # 68
Which object is used to allocate the costs from a claim to the project structure?
- A. WBS element
- B. Internal order
- C. Claim
- D. Network activity
Answer: B
NEW QUESTION # 69
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a goods receipt
- B. Saving a service entry sheet
- C. Saving a supplier invoice
- D. Saving a purchase order
Answer: A,B
NEW QUESTION # 70
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Preliminary purchase requisition for WBS element
- B. Reservation for WBS element
- C. Third-party order
- D. Purchase requisition and Reservation for WBS element
- E. Planned order
Answer: A,B,D
NEW QUESTION # 71
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
- A. WBS elements
- B. Project definition
- C. Milestones
- D. Sales order items
Answer: A,D
NEW QUESTION # 72
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.
- A. You can assign the same work center to more than one activity on the same network.
- B. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
- C. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
- D. You can assign more than one activity element to a network activity.
- E. Capacity requirements of a network activity are reduced when the activity is confirmed.
Answer: A,D,E
NEW QUESTION # 73
In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Scheduling and distribution key
- B. Capacity planner group in the network header
- C. Scheduling and capacity category
- D. Control key of an activity
Answer: D
Explanation:
To carry out the internal project work as soon as possible, you have to maintain the control key of an activity in capacity requirements planning. Capacity requirements planning is a process that determines the capacity requirements and availability for work centers or resources that are used to execute project activities. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The control key also determines whether an activity is relevant for capacity requirements planning or not. To carry out the internal project work as soon as possible, you have to use a control key that activates capacity requirements planning for the internal activities. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 74
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?
- A. WBS elements
- B. Network activity for activity-account-assigned networks
- C. Network header for activity-account-assigned networks
- D. Standard WBS elements
Answer: A,C
Explanation:
The objects that can be used to specify settlement rules are network header for activity-account-assigned networks and WBS elements. A settlement rule is a parameter that defines how the actual costs incurred for a project object are allocated, in whole or in part, to one or more receivers. A settlement rule contains various attributes, such as the receiver type, the receiver number, the settlement percentage, and so on. The objects that can be used to specify settlement rules are:
Network header for activity-account-assigned networks: A network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. A network header for activity-account-assigned networks means that the network has its activities assigned to different account assignments, such as cost centers, orders, or sales orders. A network header for activity-account-assigned networks can be used to specify a settlement rule for settling the costs of the network to one or more receivers.
WBS elements: A WBS element is a structural element of a project that represents a deliverable or a work package within a project. A WBS element can have various attributes, such as dates, costs, revenues, budgets, and so on. A WBS element can be used to specify a settlement rule for settling the costs of the WBS element to one or more receivers.
NEW QUESTION # 75
Which planning method can prevent further rescheduling of activities?
- A. Workforce planning
- B. Partial confirmation of activities
- C. Capacity levelling
- D. Capacity requirements activation
Answer: D
NEW QUESTION # 76
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question
- A. Duration
- B. Work
- C. Activity type
- D. Profit center
Answer: A,B
NEW QUESTION # 77
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?
- A. Assign One production order to a sales order
- B. Assign a network to a sales order
- C. Assign a sales order to a project with appropriate hierarchy levels.
- D. Assign Several production orders to a sales order
Answer: C
Explanation:
To avoid unnecessary stock cost, you can assign a sales order to a project with appropriate hierarchy levels. This means that you can create a project structure that matches the multilevel production environment with bill of material and routing. You can assign a sales order item to a WBS element that represents the finished product and assign production orders to WBS elements that represent the semi-finished products. This way, you can use project stock to manage the materials required for the project and avoid creating inventory for intermediate products. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
NEW QUESTION # 78
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
- A. Project planning board
- B. Easy Cost Planning
- C. Project Builder
- D. Schedule Manager
Answer: A,C
Explanation:
To plan basic dates manually for WBS elements, you can use the Project Builder or the Project planning board. These are tools that allow you to create and maintain project structures, such as WBS elements, networks, activities, and milestones. You can enter basic dates for WBS elements in the Basic Data tab of the WBS element master data in the Project Builder or in the Gantt chart view of the Project planning board. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/3673b65334e6b54ce10000000a174cb4.html
NEW QUESTION # 79
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
- A. Only capacity requirements
- B. Forward
- C. Backward
- D. Current date
Answer: C
NEW QUESTION # 80
The various work packages in the project are described as individual______________. Choose the correct answer.
- A. WBS elements
- B. Activities
- C. Tasks
- D. Project definitions
Answer: A
NEW QUESTION # 81
Dates
You want to exchange data between SAP Project System and Microsoft What interface do you use?
- A. you do not need and interface. You can exchange data using object link.
- B. The catalog interface.
- C. No interface to Microsoft Project is available.
- D. The EPS interface (External Project Software).
Answer: D
NEW QUESTION # 82
......
SAP C_TS412_2021 certification exam is a challenging exam that requires candidates to have a strong understanding of SAP S/4HANA Project Systems. Candidates are expected to have hands-on experience working with SAP S/4HANA Project Systems and to have a good understanding of the SAP implementation methodology. C-TS412-2021 exam is also designed to test the candidate's ability to work with other SAP modules, such as SAP Finance and SAP Materials Management.