NEW QUESTION 342
A company normally ships to a customer by rail at a cost of $500 per load. The transit time is fourteen days. The goods can be shipped by truck for $700 per load and transit time of four day. If transit inventory cost is $35 per day, what does it cost to ship each way?

  • A. Rail: $900 and Truck: $ 890
  • B. Rail: $990 and Truck: $ 840
  • C. Rail: $980 and Truck: $ 880
  • D. Rail: $970 and Truck: $ 870

Answer: B

 

NEW QUESTION 343
Which file contains information on the capacity and move, wait, and queue times associated with the center?

  • A. Work center
  • B. Run time
  • C. Calendar
  • D. Routing

Answer: A

 

NEW QUESTION 344
Poke-Yoke (Fail Safe) tries to change either the process or its resources, thus eliminating the need to rely on human experience and knowledge. Examples include:

  • A. Both of these
  • B. Put a template over an assembled component to show operators where specific parts go
  • C. None of these
  • D. Use color-coded parts

Answer: A

 

NEW QUESTION 345
uses the economic-order-quantity formula to calculate an economic time between orders.

  • A. inventory-carrying-order quantity
  • B. period-order quantity
  • C. All of the above
  • D. production-order quantity

Answer: B

 

NEW QUESTION 346
Giving people the authority to make decisions and take action in their work areas without getting prior approval is called:

  • A. Dominance
  • B. Empowerment
  • C. Entitlement
  • D. Intensity

Answer: B

 

NEW QUESTION 347
What includes the functions of establishing specifications, selecting suppliers, price determination, and negotiation?

  • A. Procurement
  • B. None of the above
  • C. Supplier scheduling
  • D. Competitive follow-up

Answer: A

 

NEW QUESTION 348
A systematic method by which organizations can compare their performance in a particular process to that of a "best in class" organization, finding out how that organization achieves those performance levels and applying them to their own organization, is called:

  • A. Standardization
  • B. Analyzing
  • C. Applicability
  • D. Benchmarking

Answer: D

 

NEW QUESTION 349
Control is exercised through individual items in a particular inventory, this is called:

  • A. Stock-keeping units
  • B. Inventory corps
  • C. Stock entity
  • D. Inventory element

Answer: A

 

NEW QUESTION 350
Which one of the following is Not out of five basic inputs to the manufacturing planning and control system?

  • A. Available facilities and quantities required
  • B. Time needed to perform operations
  • C. Product Description and process specifications
  • D. Customized Design

Answer: D

 

NEW QUESTION 351
The rate of production that is synchronized with the rate of customer demand is known as:

  • A. challenge
  • B. takt time
  • C. horizon time
  • D. stipulate

Answer: B

 

NEW QUESTION 352
Each of the following actions would reduce safety stock levels EXCEPT:

  • A. increase lead times
  • B. reduce the customer service target
  • C. adopt a make-to-order strategy
  • D. reduce forecast error

Answer: A

 

NEW QUESTION 353
In terms of structure and function, the construction supply chain is characterized by the following element/s:

  • A. It is, apart from rare exceptions, a temporary supply chain producing one-of construction projects through repeated reconfiguration of project organizations. As a result, the construction supply chain is typified by instability, fragmentation, and especially by the separation between the design and the construction of the built object.
  • B. It is a converging supply chain directing all materials to the construction site where the object is assembled from incoming materials. The construction factory is set up around the single product, in contrast to manufacturing systems where multiple products pass through the factory, and are distributed to many customers.
  • C. It is a typical make-to-order supply chain, with every project creating a new product or prototype. There is little repetition, again with minor exceptions. The process can be very similar, however, for projects of a particular kind.
  • D. All of these

Answer: A

 

NEW QUESTION 354
Dependency in MRP can be

  • A. Both A & B
  • B. Horizontal
  • C. None of the above
  • D. Vertical

Answer: A

 

NEW QUESTION 355
If the volume is greater than the cost equalization point, the method with the greater variable cost will cost less.

  • A. True
  • B. False

Answer: B

 

NEW QUESTION 356
Inventory investment can be balanced with:

  • A. Cost of placing orders
  • B. Customer service
  • C. Costs associated with changing production levels
  • D. All of the above

Answer: D

 

NEW QUESTION 357
The ranking of jobs for the dispatch list is created through the application of which of the following priority rule?

  • A. First come, first served
  • B. All of the above
  • C. Shortest process time
  • D. Earliest operation due date

Answer: B

 

NEW QUESTION 358
In considering open shop orders, capacity requirement planning account for:

  • A. Work already done on a shop order
  • B. Order lot size
  • C. Order requirements
  • D. Lead time

Answer: A

 

NEW QUESTION 359
Materials should be moved from point of manufacture to point of use when:

  • A. material handling equipment is available
  • B. the materials are needed at point of use
  • C. material at point of use is zero
  • D. production is completed at point of manufacture

Answer: B

 

NEW QUESTION 360
A control chart for averages and ranges tracks which critical characteristics of a frequency distribution?

  • A. shape and spread
  • B. center and spread
  • C. control and tolerance
  • D. specification limit and center

Answer: B

 

NEW QUESTION 361
What is a problem for manufacturing, but it can be attained by overtime or under-time, shifting workers, and so forth?

  • A. Capacity change
  • B. Risk disbursement
  • C. Working center control
  • D. Input/Output rate

Answer: A

 

NEW QUESTION 362
......

2022 New Actualtests4sure CPIM PDF Recently Updated Questions: https://www.actualtests4sure.com/CPIM-test-questions.html

CPIM Exam with Guarantee Updated 590 Questions: https://drive.google.com/open?id=1B3_5nA_4RF1kbGlfOllIXwDJrjg93n7K