NEW QUESTION 31
How can you update the degree of processing for an activity?
- A. By using results analysis
- B. By confirming the activity
- C. By changing the activity
- D. By scheduling the activity
Answer: B
NEW QUESTION 32
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
- A. Shift activities backward or forward on the time axis where more capacities are available.
- B. Maintain subordinate internal activity elements assigned to other work centers.
- C. Increase the capacities of the work center in the project planning board.
- D. Trigger automatic capacity leveling inside the project planning board.
Answer: A,D
NEW QUESTION 33
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.
- A. By searching via status combination code
- B. By searching for the individual status
- C. By searching via status selection profile
- D. By searching for the status profile
Answer: B,D
NEW QUESTION 34
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.
- A. The network is assigned to a sales order item.
- B. The network activity is assigned to a WBS element.
- C. The Project Stock indicator is set in the project definition (non-valuated or valuated).
- D. The material master of the component must permit project stock management.
- E. A procurement indicator must be assigned to the activity.
Answer: C,D,E
NEW QUESTION 35
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions can be created automatically based on user status.
- B. Manually created project versions always require a project version profile.
- C. Project versions are mandatory for Milestone Trend Analysis (MTA).
- D. Project versions can be changed.
Answer: C,D
NEW QUESTION 36
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
- A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- B. Set up the requirement date manually as February 5.
- C. Set up the requirement date aligned with the activity start date and an offset of 5 days.
- D. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
Answer: C
NEW QUESTION 37
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. The purchase order is updated automatically to match the new quantity while saving the project.
- B. The system automatically creates a new purchase requisition with the difference to the original quantity.
- C. A workflow can be triggered to inform the purchasing group.
- D. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
Answer: C
NEW QUESTION 38
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.
- A. Relationships can be used to connect activities of different networks.
- B. Material components can be assigned to activity elements.
- C. A network can be activity-account-assigned and header-account-assigned.
- D. A network activity can be assigned to several WBS elements.
Answer: A,C
NEW QUESTION 39
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?
- A. Top-down
- B. Bottom-up
- C. Strict bottom-up
- D. Free planning
Answer: B
NEW QUESTION 40
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A. Activity
- B. Milestone
- C. Activity element
- D. Network header
Answer: A
NEW QUESTION 41
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Network profile
- B. Network type
- C. Project profile
- D. Parameters for the network type
Answer: D
NEW QUESTION 42
Which object is used to allocate the costs from a claim to the project structure?
- A. WBS element
- B. Network activity
- C. Claim
- D. Internal order
Answer: D
NEW QUESTION 43
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
- A. Structure overview
- B. None
- C. Extended capacity evaluation
- D. Individual overview capacity requirements
- E. Capacity load work center view
Answer: D
NEW QUESTION 44
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.
- A. A header-account-assigned network that is assigned to a sales order item
- B. An activity-account-assigned network that is assigned to a sales order item
- C. A dynamic item processor (DIP) profile with the appropriate settings
- D. Released WBS elements, activities, and/or activity elements
Answer: C,D
NEW QUESTION 45
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
- A. Hierarchical reports
- B. Resource reports
- C. Structure information system reports
- D. Cost element reports
Answer: C
NEW QUESTION 46
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Progress analysis
- B. Results analysis
- C. Settlement
- D. Milestone trend analysis
- E. Confirmations
Answer: A,B,C
NEW QUESTION 47
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.
- A. Profit center
- B. Work
- C. Activity type
- D. Duration
Answer: B,C
NEW QUESTION 48
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
- A. Milestones
- B. Project definition
- C. Sales order items
- D. WBS elements
Answer: C,D
NEW QUESTION 49
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing material availability
- B. Missing authorizations to release material components
- C. Missing reservations for material components
- D. Missing budget for material components
Answer: B
NEW QUESTION 50
What is the reason for assigning billing plans in customer projects?
- A. Billing plans enable the billing process to be carried out.
- B. Billing plans are used for revenue planning.
- C. Billing plans are copied automatically to the sales order item.
- D. Billing plans are prerequisites for quotation creation.
Answer: A
NEW QUESTION 51
What could be a reason to use expert mode in the valuation method for results analysis?
- A. Assignments of different accounts for postings to financial accounting
- B. Usage of different line IDs
- C. Billing WBS elements belonging to different company codes
- D. Valuation in different currencies
Answer: A
NEW QUESTION 52
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.
- A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
- B. You can only maintain the actual start of a WBS element if the finish date is not maintained.
- C. You can always maintain the actual start and finish date of a WBS element.
- D. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".
Answer: A,D
NEW QUESTION 53
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?
- A. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
- B. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
-> Purchase order monitoring -> Goods receipt -> Invoice receipt - C. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
- D. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
Answer: C
NEW QUESTION 54
......