SAP C_TS412_1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Dates > 12% | Describe the importance of various dates which can be tracked for projects |
| Revenues and Payments > 12% | Describe the characteristics of Revenues & Payments. |
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
SAP C_TS412_1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
NEW QUESTION 34
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A delivery document type must be configured.
- B. A sold to party is necessary.
- C. A shipping point is necessary.
- D. A sales order must be created in advance.
Answer: B,C
NEW QUESTION 35
How can you grant individual authorization for WBS elements and networks?
- A. Define a user status to lock the business transaction Update Project.
- B. Set the system status to "Lock Master Data".
- C. Activate access control lists (ACL) for the project profile and the network profile.
- D. Activate access control lists (ACL) for the user master record.
Answer: C
NEW QUESTION 36
Which planning method can prevent further rescheduling of activities?
- A. Capacity requirements activation
- B. Capacity leveling
- C. Workforce planning
- D. Partial confirmation of activities
Answer: A
NEW QUESTION 37
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.
- A. Quotation
- B. Billing
- C. Sales order
- D. Inquiry
Answer: A,C
NEW QUESTION 38
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?
- A. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
- B. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
- C. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
-> Purchase order monitoring -> Goods receipt -> Invoice receipt - D. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
Answer: D
NEW QUESTION 39
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Data entry profile
- B. Project profile
- C. Network profile
- D. Network type
Answer: A
NEW QUESTION 40
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.
- A. Profit center
- B. Activity type
- C. Duration
- D. Work
Answer: B,D
NEW QUESTION 41
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Cost element report on budget updates
- B. Structure overview for budgets
- C. Hierarchical report on budget updates
- D. Line item report for budgets
Answer: D
NEW QUESTION 42
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.
- A. The factory calendar in the work center used for the internal processing activity
- B. The relationships between activity elements
- C. An activated Scheduling indicator in the control key of the internal processing activity
- D. Whether the work for the internal activity is greater than its duration
- E. The unit (for example, hour, day) of the field Normal Duration field of the activity
Answer: A,B,C
NEW QUESTION 43
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?
- A. Calculation of actual values
- B. Activity allocation
- C. Goods receipt for purchase orders
- D. Creation of purchase orders
Answer: D
NEW QUESTION 44
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.
- A. The Project Stock indicator is set in the project definition (non-valuated or valuated).
- B. The network is assigned to a sales order item.
- C. The material master of the component must permit project stock management.
- D. The network activity is assigned to a WBS element.
- E. A procurement indicator must be assigned to the activity.
Answer: A,C,E
NEW QUESTION 45
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. Network activity
- B. BOM item
- C. WBS element
- D. Material master
Answer: A,B
NEW QUESTION 46
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.
- A. If the reduction strategy is set in the network header
- B. If the appropriate reduction type is set in the parameters for network scheduling
- C. If the maximum reduction level is less than 100
- D. If the reduction strategy is set in each activity
Answer: A,B
NEW QUESTION 47
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?
- A. The manual hierarchical revenue planning will be displayed only if expert mode is activated.
- B. Cost element reports can display costs but not revenues.
- C. The manual hierarchical revenue planning has no reference to cost elements.
- D. Cost element reports display integrated planning only.
Answer: C
NEW QUESTION 48
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A. Network header
- B. Milestone
- C. Activity
- D. Activity element
Answer: C
NEW QUESTION 49
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Planned revenue can be transferred from a sales quotation.
- B. Planned revenue requires a sales order assigned to a WBS element.
- C. Actual revenue is posted via a billing plan assigned to a WBS element.
- D. Actual revenue is posted via a billing document created from a sales order
Answer: A,D
NEW QUESTION 50
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
- A. Maintain subordinate internal activity elements assigned to other work centers.
- B. Increase the capacities of the work center in the project planning board.
- C. Shift activities backward or forward on the time axis where more capacities are available.
- D. Trigger automatic capacity leveling inside the project planning board.
Answer: C,D
NEW QUESTION 51
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.
- A. By default, critical activities have a float time, which is less than or equal to zero.
- B. The float time of WBS elements is calculated by extrapolation.
- C. The maximum size of a free float is as large as the total float of an activity.
- D. Activities with the time constraint "Must start on" always have a negative float time.
- E. Float time can be negative.
Answer: A,D,E
NEW QUESTION 52
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.
- A. To start workflow tasks
- B. To set an actual finish date for WBS elements
- C. For trend analysis
- D. To transfer the actual date to the billing plan
Answer: C,D
NEW QUESTION 53
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. A workflow can be triggered to inform the purchasing group.
- B. The system automatically creates a new purchase requisition with the difference to the original quantity.
- C. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
- D. The purchase order is updated automatically to match the new quantity while saving the project.
Answer: A
NEW QUESTION 54
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The availability check for material components indicates missing parts.
- B. The material master is set to external procurement.
- C. The material is assigned to the activity as a non-stock material.
- D. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
Answer: A,D
NEW QUESTION 55
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.
- A. You can shorten the project mask even when there are existing projects.
- B. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.
- C. You can use the same coding mask for standard projects and operative projects.
- D. You can only use numbers for a project coding mask definition.
Answer: B,C
NEW QUESTION 56
......